Arlington Virginia ADU Permit Process: A Real Builder’s 2025 Timeline
Miranda Carter
Introduction
As a LEED Green Associate and real estate professional who’s currently navigating Arlington’s ADU permit process for my own sustainable modular home prototype, I’ve learned firsthand what it really takes to build an ADU in Arlington County. Here’s the complete timeline and insider knowledge you won’t find anywhere else.
ADU Process for a Newbie- Based on My Experience
SURVEY/PLAT
1 – 2 Weeks
DESIGN PROCESS
Not only with your team but Arlington County to ensure no issues when applying for permits.
ADDRESS APPLICATION
I applied during the holiday season – it took some time
Accessory Dwelling Permit
Declaration of Covenants
Compliance Agreement
Final Zoning Meeting
Building Permit
Water Connection
Mechanical
Plumbing
Electrical
Construction & Inspections
Certificate of Occupancy
ADU Considerations
The pricing:
Materials Budget: wide range depending on your choices
Labor
Foundation Work
Utility connections
Survey and design fees
Multiple permit fees
Other Considerations
Traditional stick-built tends toward the higher end
Modular/prefab solutions can significantly reduce costs
Why Modular Makes Sense
After going through this process, here’s why modular is the smart choice:
Speed: Factory construction happens while permits are processing – no weather delays
Efficiency: Precise manufacturing reduces waste and ensures consistent quality
Sustainability: Better insulation, energy efficiency, and sustainable materials standard Predictable Costs: Less risk of cost overruns during construction
Next Steps
Contact Permit Arlington – Your main point of contact for all questions
Get your property surveyed – Essential first step
Determine your budget – Be realistic about total project costs
Consider modular options – Can save months and reduce complexity.
Ready to explore sustainable, efficient ADU solutions?Contact Green Luxe Pods to learn how our LEED-certified modular homes can streamline your Arlington ADU project.